| NUNAM IQUA AIRPORT RUNWAY EXTENSION | |||||||||||||||||||||||||||||||||||||
| Nunam Iqua Runway Extension ADOT&PF Project No. 61444 | |||||||||||||||||||||||||||||||||||||
| Printable version of Nunam Iqua Runway Extension scoping letter | |||||||||||||||||||||||||||||||||||||
| The Alaska Department of Transportation and Public Facilities (ADOT&PF), in cooperation with the Federal Aviation Administration (FAA) is proposing to rehabilitate and upgrade the existing Nunam Iqua Airport to meet current FAA safety guidelines. Nunam Iqua (formerly known as Sheldon Point) is located on the southwest bank of Kwemeluk Pass on the Yukon River Delta, approximately 18 miles southwest of Emmonak and 500 miles west-northwest of Anchorage (Figure 1), in Sections 9 and 10 of Township 28 North, Range 84 West, Seward Meridian (USGS Quad Kwiguk C-6). | |||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||
Existing Condition The existing airport facility consists of a 60 x 3,015-foot gravel runway (Runway 2-20), oriented south-southwest to north-northeast. The runway has a 120 X 3,495-foot safety area, and a 50-foot wide taxiway. The facility also has a 200 X 200-foot apron, as well as a 100 X 200-foot temporary apron adjacent to the 40 X 50-foot SRE building. The runway is equipped with a medium-intensity runway lighting (MIRL) system. The gravel surface is in fair condition, but doesn't perform well in spring months. |
|||||||||||||||||||||||||||||||||||||
| Purpose
and Need The purpose of the proposed work is to address several deficiencies at the Nunam Iqua Airport with regards to airport safety and maintenance of the runway and apron. The need for the proposed project is to upgrade the runway and airport to current FAA standards. The following deficiencies will be addressed in the environmental document: |
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||
Preliminary Research
Results In addition to identifying any concerns and/or issues your agency might have with the proposed project, the links below identify agency specific information that is requested. Please click on the organization that you represent. This will take you to a list of questions specific to your purview and a link that allows you to provide comments directly to our environmental consultant, via e-mail. |
|||||||||||||||||||||||||||||||||||||
| To ensure that all factors are considered in the environmental document, your comments are requested by Friday, August 26, 2005. If you have any questions regarding the project please contact Kristen Hansen, Environmental Consultant with DOWL Engineers, at 562-2000, or by e-mail at khansen@dowl.com or contact me at (907) 451-5129 or by e-mail at ryan_anderson@dot.state.ak.us. | |||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||