| Following
is the estimated dates for projects in the area: |
| Phase
I |
| |
|
16th
Avenue/Muldoon Road Intersection Improvements Construction |
Fall
2005 |
| |
|
Private
Development adjacent to
16th Avenue |
Begins
Spring 2006 |
| |
|
Muldoon
Middle School construction
(opens Fall 2007) |
2005
to August 2007 |
| |
|
Roadway
Design and Environmental Documentation |
2004
to 2005 |
| |
|
-
|
Creekside
Parkway |
|
| |
|
- |
DeBarr
Road |
|
| |
|
-
|
Muldoon
Road |
|
| |
|
Utility
Upgrades |
| |
|
- |
AWWU
Phase 1 Water Line on
DeBarr Road
(Patterson to 600' east of Patterson) |
Summer
2004 |
| |
|
CEA
and GCI Utility Undergrounding |
Summer
2006 |
| Phase
II |
| |
|
Creekside
Parkway/Debarr Road Intersection Design |
2005-2006 |
| |
|
Creekside
Parkway/Debarr Road Intersection Construction |
Summer
2006/2007 |
| |
|
Utility
Upgrades |
|
| |
|
-
|
AWWU
Phase 2 Water Line on
DeBarr Road
(Summit View to Muldoon Road) |
Summer
2006/2007 |
| |
|
- |
CEA
Overhead Utility Line Relocation |
Summer
2006 |
| |
|
Roadway
Construction |
2005
to 2007 |
| Phase
III |
| |
|
Last
phase of Creekside Center Drive construction including bridge over Chester
Creek |
2006
to 2010 |
| |
|
Creekside
Town Center
Private Development |
2005
to 2010 |