Funding
The vast majority of the $25 million in funding for these improvements are requested earmarks coming from Federal TEA-21. Additional sources of funding include State grants and local bond issues.
Meetings
Public Meeting Number 2 - March, 2006
  Northeast Community Center, 1251 Muldoon Road, Anchorage 7:00 - 9:00 p.m.
Construction Schedule
Following is the estimated dates for projects in the area:
Phase I
  16th Avenue/Muldoon Road Intersection Improvements Construction Fall 2005
  Private Development adjacent to
16th Avenue
Begins Spring 2006
  Muldoon Middle School construction
(opens Fall 2007)
2005 to August 2007
  Roadway Design and Environmental Documentation 2004 to 2005
    - Creekside Parkway  
    - DeBarr Road  
    - Muldoon Road  
  Utility Upgrades
    - AWWU Phase 1 Water Line on
DeBarr Road
(Patterson to 600' east of Patterson)
Summer 2004
  CEA and GCI Utility Undergrounding Summer 2006
Phase II
  Creekside Parkway/Debarr Road Intersection Design 2005-2006
  Creekside Parkway/Debarr Road Intersection Construction Summer 2006/2007
  Utility Upgrades  
    - AWWU Phase 2 Water Line on
DeBarr Road
(Summit View to Muldoon Road)
Summer 2006/2007
    - CEA Overhead Utility Line Relocation Summer 2006
  Roadway Construction 2005 to 2007
Phase III
  Last phase of Creekside Center Drive construction including bridge over Chester Creek 2006 to 2010
  Creekside Town Center
Private Development
2005 to 2010